The topping out party for Blunt Hall will be held on May 22. The top beam will be placed at 1 PM on May 22. I hope to see you there.
BLUNT HALL
5/13/24 5/31/24 – Existing East Stairwell & Fourth Floor Existing Office shoring and concrete removal (Avoid east hallway and stairwell).
5/13/24 thru 8/9/24 – Levels 2, 3, & 4 New Restroom Construction (Restrooms on these floors will be offline for the duration of the work – that’s all summer!)
6/1/24 to 6/2/24 – All Building Power Outage – Watch for more information from Ben Boslaugh
6/10/24 thru 7/31/27 – Plaster Stadium Sidewalk closed for retaining wall work.
Kemper Hall Construction News
JQH Parkway will be closed between Briggs Street and the Blunt Loading Dock starting May 13 for approximately 2 weeks. There will be no access to lot 19. Sidewalks will be closed.
Brightspace
Brightspace will be the only LMS available for all classes starting May 13, 2024. Blackboard is totally gone on in June – gradebooks, course materials – everything will be gone and not be accessible. Just a quick reminder. Faculty Handbook Section 4.5.1.10. University-wide Learning Management System “ All faculty members shall use the university-wide learning management system to provide an electronic copy of the course syllabus and schedule, communicate class cancellations and schedule changes, and post student grades.” FCTL if offering help for those who need it to start using the new LMS. I just had a one-on-one appointment to save my Blackboard course into a source course in Brightspace. It went very quickly and easily. Brightspace – Faculty Center for Teaching and Learning – Missouri State
SOAR
SOAR – sessions begin on June 3 and run until July 25. There will be a single day SOAR session on May 31 for students attending summer classes and then another one day SOAR session on August 15 if a student couldn’t attend a standard session over the summer.
United Way
United Way Day of Caring is June 13, 2024. There are three ways you can participate. Click here for more information – Human Resources (missouristate.edu)
NSF MRI Proposals
NSF MRI Proposals 2024 – The submission window is October 15 – November 15. The internal competition will be sometime in July. Major Research Instrumentation Program (MRI) | NSF – National Science Foundation
Recent news from the college:
CNAS Faculty Staff Awards website has been updated – Faculty and Staff Awards – Faculty and Staff Resources – College of Natural and Applied Sciences – Missouri State
CNAS Undergraduate Research Day website has been updated with the program and all of the winners
CNAS Undergraduate Research Symposium – College of Natural and Applied Sciences – Missouri State
- If you would like to see past stories please visit CNAS NewsWatch!
Construction Updates
Blunt (Temple Hall) Construction Details. If you have questions, please contact the Dean’s Office email directly BluntHallConstruction.edu
5/20/24 thru 5/24/24
5/22/24 – Topping Out @ 1:00 pm (gather at west mall)
5/23/24 – Generator placed in utility yard (Crane on Briggs Street near stadium ramp)
- Electrical and plumbing work in addition – Levels 2, 3 & 4.
- Interior metal stud framing on Level 2, 3 & 4 and new restrooms.
- Gypsum board installation Level 1 & 2
- Concrete and shoring company demobilization.
5/27/24 Memorial Day – No work
5/28/24 thru 5/31/24
- Electrical and plumbing work in addition – Levels 3 & 4.
- Interior metal stud framing on Level 3 & 4.
- Gypsum board installation Level 1 & 2 and new restrooms.
- Concrete and shoring company demobilization complete.
- Door frames commence on Level 0.
6/1/24 to 6/2/24 – All Building Power Outage
6/3/24 thru 6/14/24
- Electrical and plumbing work in addition – Levels 3 & 4.
- Interior metal stud framing on Level 3 & 4.
- Gypsum board installation Level 1 & 2 and new restrooms.
- New restroom tile installation.
- Roofing installation commences.
Calendar
- May 22 Topping out celebration – 1 PM
- May 13-31 Summer Intersession
- June 3 Summer Courses begin today along with SOAR
- June 19 Juneteenth – University Closed – no classes
- June 28 Summer Visit Day
- July 4-5 University closed – no classes
- July 19 Summer Visit Day
- July 26 Summer session ends (finals complete)
- August 12 New Faculty and New Graduate Student orientations begin today
- August 14 Showcase (FCTL) – speaker is a CNAS graduate
- August 15 All Faculty Luncheon
- August 18 New Student convocation
- August 19 First day of the fall 2024 semester
- August 19 CNAS All Faculty meeting, Meyer Libr 101, 3:00-5:00
Media
- Subscribe to follow CNAS NewsWatch (also available on CNAS homepage)
- Find Dean Jahnke’s past eblasts and subscribe to CNAS Blog.
- Tune in every Thursday morning at 9:45 a.m. for 5-minute Astro Brief on KSMU.