Planning, Design & Construction announces a closure associated with the following project:
16-062 Improve District Chilled Water System, Campus Utilities
The Improve District Chilled Water System, Campus Utility Project was unsuccessful in completing our Cherry Street road crossing. The project will continue next week with an anticipated road opening the first part of the week. Pipe installation work on the North side of Cherry street to the West will continue thru next week. Further updates will be provided as information becomes available.
Questions regarding this closure can be directed to Mark Frietchen.