IMPORTANT: 2026 Annual Steam Outage will happen May 9th-13th, 2026

May 6, 2026 by Janae J. Kiely

The 2026 Annual Steam Outage will occur May 9 – 13, 2026. Each year it is necessary to shut down the campus steam system to perform required inspections and essential maintenance on the campus steam system.  This outage helps ensure our steam system remains reliable and safe. During the outage, some buildings on campus may be colder than usual, and domestic hot water may not be available.

Begins 12:01 am Saturday, May 9th.

District Steam System to be restored the evening of Wednesday, May 13th.

Facilities impacted are (in alphabetical order):

  1. Baker Bookstore – HVAC
  2. Blair Shannon House – HVAC, Domestic Hot Water, and Food Service
  3. Blunt Hall (to include the Vivarium) – HVAC, Humidity, Autoclave, and Domestic Hot Water
  4. Carrington Hall – HVAC
  5. Cheek Hall – HVAC
  6. Craig Hall – HVAC
  7. Ellis Hall – HVAC (Humidity Control)
  8. Forsythe Athletic – HVAC and Domestic Hot Water
  9. Foster Family Recreation Center – HVAC, Domestic Hot Water, Pool Heat, and Spa.
  10. Freudenberger House – HVAC and Domestic Hot Water
  11. Greenwood Lab School – HVAC and Domestic Hot Water
  12. Hill Hall – HVAC
  13. Karl’s Hall – HVAC and Domestic Hot Water
  14. Kemper Hall – HVAC
  15. Majors Health and Wellness Center – HVAC and Domestic Hot Water
  16. McDonald Arena – HVAC and Domestic Hot Water
  17. Meyer Library – HVAC and Humidity
  18. Plaster East Bleachers – HVAC and Domestic Hot Water
  19. Plaster Stadium – HVAC and Domestic Hot Water
  20. Plaster Student Union – HVAC (Domestic Hot Water will be on the Electric Back-Up)
  21. Pummill Hall – HVAC and Domestic Hot Water
  22. Siceluff Hall – HVAC and Domestic Hot Water
  23. Strong Hall – HVAC and Domestic Hot Water
  24. Telecommunications – HVAC
  25. Wells House – HVAC and Domestic Hot Water
  26. Woods House – HVAC and Domestic Hot Water

Art Annex impact is TBD.  The facility is still under construction.

If you have any questions or concerns, please contact Work Management at 417-836-8400 or by email to workmanagement@missouristate.edu. Thank you!


Discover more from Administrative Services Notifications

Subscribe to get the latest posts sent to your email.

Filed Under: Administrative Services, Planning, Design & Construction

Recent Posts

  • Closure Notification – West Entrance, Cheek Hall
  • MSU Parking Permits Go Virtual for 2026-2027
  • Campus Impact (Update) – Judith Enyeart Reynolds Complex
  • Campus Impact – Judith Enyeart Reynolds Complex
  • Bear Park South Reopens for Campus Parking

Recent Comments

  • Employee Welcome Back, Mocktails, Bug Bites, Back to School Support - Wellness Works on Closure Notification – West Entrance, Cheek Hall
  • Five Things (plus a Few More!) - This Week in the Division of Student Affairs - July 13th - Student Affairs Blog on MSU Parking Permits Go Virtual for 2026-2027
  • Six Month Classes, Movement Challenge, Cardinal Tickets, Discounted Fair Tickets - Wellness Works on MSU Parking Permits Go Virtual for 2026-2027

Archives

Categories

  • Administrative Services
  • Custodial Services
  • Facilities Management
  • Job Fair
  • Parking
  • Planning, Design & Construction
  • Safety and Transportation
  • Shuttle
  • Uncategorized
  • University Support Services

Meta

  • Log in
  • Entries feed
  • Comments feed
  • WordPress.org
  • Accessibility
  • Disclaimer
  • Disclosures
  • Equal Opportunity Employer and Institution
  • © 2026 Board of Governors, Missouri State University
  • Contact Information